Dubai Metro Blue Line 29% Complete; Sheikh Hamdan Confirms 2029 Opening
Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, announced on Sunday that construction of the Dubai Metro Blue Line is around 30 per cent complete. The project is scheduled to begin operations on September 9, 2029.
According to Khaleej Times, Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum visited Dubai Festival City on Sunday, November 22, 2026, to review progress on the Dubai Metro Blue Line project.
The Crown Prince of Dubai said around 14,000 workers, engineers and supervisors are involved in the project, with a total of 33 million person-hours recorded.
Noting the accelerated pace of construction, he said: “Work on the project is gathering pace to ensure it opens as scheduled on September 9, 2029.”
New designs for Dubai Metro trains and stations
During the visit, Sheikh Hamdan was briefed on the innovative design of the new trains and the modern interiors of the Dubai Metro Blue Line stations.
The Crown Prince of Dubai said the Roads and Transport Authority (RTA) is also using artificial intelligence to inspect rail infrastructure and carry out maintenance operations.
Middle East’s first train systems development laboratory to open
Sheikh Hamdan also highlighted the RTA’s plan to establish a new research and development centre in partnership with CASCO Signal.
He said the centre will house the Middle East’s first train systems development laboratory.
According to the Crown Prince of Dubai, the centre aims to achieve the highest standards of operational readiness, safety and reliability for rail systems.
The RTA previously announced plans to establish the centre in July, saying its activities would support not only the Dubai Metro Blue Line but also future metro expansion projects across the emirate.
Metro Systems to Be Tested Before Operations Begin
Unlike traditional research laboratories, the new research and development centre will simulate real-world train operating conditions.
This capability will allow engineers to test signalling, communications and train control systems before they are deployed across the metro network.
The centre will also assess the interoperability of various technologies in terms of safety and efficiency, allowing potential technical issues to be identified and resolved before passenger services begin.
Under the announced schedule, the Dubai Metro Blue Line is set to open on September 9, 2029, with construction progressing through the efforts of thousands of workers and specialists.